Campus Planning and Facilities Management has updated its running list of closures and other activities that affect travel, access and planning on campus.
The office broadcasts important campus notifications in a variety of ways to keep the university community informed about building maintenance, emergency management testing, construction and other campus planning and facility projects.
The latest notifications include:
New:
- Reminder: 1715 Franklin, Knight Law Center, Beall Hall, Berwick Hall fire system testing and maintenance, week of July 11-15.
- Huestis Hall, Lokey Labs, LISB and Streisinger, Deschutes, Carson, Willamette and Klamath halls noise and vibration advisory, July 11-13.
- Lokey Education south side restroom shutdown, through July 8.
- Villard and University halls inspection advisory, July 11-13.
- 1715 Franklin parking during OR22, July 14-24.
- 1715 Franklin access advisory, July 11-29.
Ongoing:
- Baker Downtown Center restrooms 201A and 202A shut down until city of Eugene repairs sewer line, May 31-unknown.
- Campus academic buildings manual unlocking/locking schedule, summer 2022.
- Campus air handling unit preventative maintenance scheduled for July 2022 includes Thompson University Center, Prince Lucien Campbell Hall, EC Cares Whiteaker classrooms, EC Cares Westmoreland classrooms, EC Cares main office and Condon Hall.
- Campus fire systems testing and maintenance schedule for summer 2022. Reminders will be sent out a week prior to each building’s test.
- Computing Center second-floor emergency air conditioning shutdown due to damaged chilled water coil, July 1-unknown.
- CPFM Back 40 thermal tank storage project advisory, Jan. 31-Sept. 30.
- CPFM Back Forty access advisory due to construction activity, May 23-July 31.
- Frohnmayer Music heating system repair, Feb. 1-unknown.
- Gerlinger Annex first-floor steam heat shut down due to leak, March 30-unknown.
- Hamilton/Walton Residence Hall Transformation Project phase II, July 6, 2021-Aug. 1, 2023.
- Huestis Renovation Project site logistics for next phase, March 31, 2022-Dec. 31, 2023.
- Lawrence wheelchair lift (E271) shut down for repairs, Oct. 13-unknown.
- NILI, 1629 Moss St., HVAC shutdown to remove pest odor, Feb. 21-unknown.
- Science complex buildings access advisory during Oregon22, July 14-25.
- South Bank Path advisory to stay off the recently seeded area Oct. 19, 2021-summer 2022.
- Volcanology steam heat shutdown to repair leak, May 13-approximately Sept. 30.
- Zebrafish International Resource Center addition construction advisory, July 2, 2021-extended to Aug. 17, 2022.