Campus Planning and Facilities Management has updated its running list of closures and other activities that affect travel, access and planning on campus.
The latest notifications include:
- Landscape work at 1715 Franklin, July 10-27, in preparation of August painting.
- Weekend parking lot closures allow for summer lot painting, July 21-22, 28-29.
- Building fire alarm testing continues until Aug. 16.
- Phase 4 and 5 of steam tunnel project to impact heat systems.
- PeaceHealth North elevator modernization through Nov. 30.
The planning office broadcasts important campus notifications in a variety of ways to keep the university community informed about building maintenance, emergency management testing, construction and other campus planning and facility projects.
Employees can stayed informed by visiting the UO maps on shutdowns and construction projects or the campus closures, shutdowns and detours website.